Schwalbe Baugesellschaft mbH & Co. KG

Schwalbe Baugesellschaft is one of the construction firms with its own railway licence. This page explains track surveying – the invisible basis of every track worksite.

Also known as: Schwalbe Baugesellschaft

GermanyGermanyInfrastructure & railway construction8 min read

Key takeaways

  • No track construction without surveying. Every position and height correction needs a target value beforehand.
  • A track has several measurements at once: gauge, cant, alignment, longitudinal level and twist.
  • Fixed points are the silent infrastructure – without them there would be no reference for machines to work to.
  • Measurement happens twice: before the work for the target value, afterwards for verification.
  • Worksites remain off-limits. Surveying work happens right in the track, often in darkness.
Contents
  1. 1.What is Schwalbe Baugesellschaft mbH & Co. KG?
  2. 2.Track surveying: the invisible foundation
  3. 3.The measurements on the track
  4. 4.Vehicles used for surveying and track alignment
  5. 5.How to recognise surveying work
  6. 6.Common mix-ups
  7. 7.Conclusion

Fact file

Business areaConstruction services connected to railway operations
Legal formGmbH & Co. KG – partnership with a liable limited company
Name element"Schwalbe" as a family or company name, "Baugesellschaft" (construction company) as the purpose
Role in the networkConstruction firm with its own licence to run on the rail network
Subject to changeWorksites, vehicles and areas of operation change constantly – check the current state

How to recognise this operator

Is this really Schwalbe Baugesellschaft mbH & Co. KG?

Tick off everything that applies to the train you are looking at right now.

  • Company name states Baugesellschaft (construction company) rather than a transport term – the focus lies in construction
  • The legal-form suffix mbH & Co. KG distinguishes the firm from similarly named operations
  • Recognisable on the track by instruments on tripods, measuring trolleys and marked fixed points
  • Vehicles mostly carry warning colours and markings showing the keeper
  • Work often takes place at night or in short windows when the line is clear

Updated: August 2026 – Before the first machine gets to work at a track worksite, someone stands there with a tripod. What comes out of it is invisible later on – and yet the whole success of the construction depends on it. Schwalbe Baugesellschaft mbH & Co. KG is one of the construction firms with its own railway licence, and this page is devoted to the most invisible part of its trade: track surveying.

Spotted a worksite by the track?

Vehicles and machines change daily – record what you see while it's still there.

Download Traintrack on the App Store4.8(23 ratings) Get Traintrack on Google Play4.4(35 ratings)

What is Schwalbe Baugesellschaft mbH & Co. KG?

Schwalbe Baugesellschaft mbH & Co. KG is a construction firm connected to railway operations. The name follows a classic pattern: a company or family name, plus a designation of purpose and a legal-form suffix. From the suffix “Baugesellschaft” (construction company) comes the classification – the focus lies in construction, not transport.

Details on worksites, vehicles or clients are deliberately left out here: these are variable quantities that change faster than any database can keep up with. What holds true over time is the craft behind it.

Why construction firms need a railway licence

Anyone working on the track has to get vehicles and materials there – via the track. Having its own licence saves constantly buying in journeys from other operators and makes scheduling reliable. This turns a construction firm into a railway operator at the same time, with all the requirements on staff, vehicles and safety management that entails.

Track surveying: the invisible foundation

A track is never lying exactly where it was planned. Traffic load, subsoil, temperature and time shift it – millimetre by millimetre, but constantly. Surveying answers the one question that matters before every correction: where is the track now, and where should it be?

Establish a reference

Fixed points beside the track, often marked on masts, record the planned position on the ground. Without them there's no scale for anything that follows.

Record the actual position

Instruments on tripods, hand-held devices or measuring vehicles capture the actual position in height and alignment.

Compare target and actual

The difference produces the instruction: by how much a point needs to be raised or shifted sideways.

Hand over the setting-out

These values go to the construction machine. Only then does a tamping machine know where to bring the track.

Re-measure the result

After the work, the achieved state is documented – as verification and as the starting value for the next maintenance cycle.

The crucial point here is that without a target value, a machine can only carry forward the existing state. A tamping machine lifts and lines the track relative to what it finds – if no one specifies where the track should actually lie, the result is an evenly tamped track that’s still in the wrong place. That’s exactly why surveying in track construction, often handled by engineering firms such as IGEBA Ingenieurgesellschaft Bahn, matters so much: it supplies the only independent reference in the whole process.

Adding to the difficulty, the reference points themselves can change. Masts settle, structures move, and after major works old fixed points no longer hold. That’s why surveying always includes checking the reference system too – work that stays completely invisible from outside, yet decides whether everything fits together in the end.

The measurements on the track

Measurement What it describes Why it matters
Gauge Distance between the rails Too narrow or too wide endangers safe wheel running
Cant Height difference between the two rails on a curve Offsets centrifugal force, determines the permitted speed
Alignment Sideways deviation from the target course Directly affects ride quality and wear
Longitudinal level Height profile along the track Dips cause impacts and speed up deterioration
Twist Change in cant over a stretch Excessive values load bogies unevenly

Comparably positioned companies can be found under GBM Gleisbau Maas, Hans Strube Gleisbau, Hochbau, Tiefbau and Deutsche Gleisbau Material Transport.

Capture rare engineering vehicles

Measuring and work vehicles are one-offs – a documented sighting is genuine archive work.

Download Traintrack on the App Store4.8(23 ratings) Get Traintrack on Google Play4.4(35 ratings)

Vehicles used for surveying and track alignment

Surveying happens partly on foot with instruments, partly with vehicles that generate target values directly for the machines that follow. After that, heavy machines take over the actual correction.

For setting-out and measuring in, there’s the Plasser & Theurer EM-SAT 120, whose task lies precisely in this preparation. The subsequent correction is carried out by tamping machines such as the Plasser & Theurer 09-4X Dynamic. For work beside the track, road-rail machines such as the Atlas 1604 ZW are used. The guide to identifying classes shows how to systematically classify such vehicles.

How to recognise surveying work

Anyone regularly travelling the same route can even place these signs in time: markings and survey points appear first, then material deliveries at access points follow, and finally the machines move in. Weeks can pass between the first and last step – a period in which it’s excellent to document how a construction project takes shape.

Surveying is the quietest part of a worksite – and often happens weeks before the actual construction. Anyone who knows the signs sees a worksite coming before it’s even set up.

Have you read the situation correctly?

Tick off what you've observed – from four ticks the assessment is solid.

  • Instruments on tripods beside the track
  • Coloured markings on sleepers or rail foot
  • People with a levelling staff, reflector or hand-held device
  • Work vehicle moving noticeably slowly
  • Points or plaques on masts beside the track
  • Place, date and time noted

How to keep such observations organised long-term is described in the guide on keeping a sightings log.

Work areas on the track are off-limits

Surveying takes place in and directly beside the track – sometimes with traffic still running on the neighbouring track, sometimes at night. Barriers, construction fences and operational railway land are binding limits. Observe only from publicly accessible locations at a safe distance, as described in the article on safe distances at the track. Don't speak to workers: they have safety duties where distraction is dangerous.

Common mix-ups

Because surveying work is quiet and unobtrusive, it’s regularly misread – sometimes as a worksite, sometimes as a fault, sometimes not noticed at all. This list sorts out the most common cases.

  • Surveying and route measurement runs – this is about the worksite on the ground, not measuring trips across the whole network.
  • Marking and graffiti – coloured marks on sleepers and rails are work instructions, not vandalism.
  • Construction firm and infrastructure manager – the firm works under contract, the route doesn’t belong to it.
  • Tripod equals camera – surveying instruments look like cameras from a distance.
  • Quiet worksite equals a break – preparation and surveying often run long before a machine arrives.

Conclusion

From the outside, track construction looks like heavy machinery and lots of ballast. In fact, every worksite begins and ends with numbers: the actual position beforehand, the target position during, and the verification afterwards. Anyone who knows this sees, in a tripod beside the track, the start of an entire construction project.

In short

No correction without a target value: track surveying supplies the numbers every machine works to. It's recognisable by tripods, markings and fixed points – long before the worksite becomes visible.

Collect construction and measuring vehicles

One-offs, small series, rare deployments – document them before they move on.

Download Traintrack on the App Store4.8(23 ratings) Get Traintrack on Google Play4.4(35 ratings)

Summary

  • Schwalbe Baugesellschaft mbH & Co. KG is a construction firm with its own railway licence.
  • Track surveying supplies the target values by which machines bring a track into position and height.
  • Gauge, cant, alignment, longitudinal level and twist are each measured separately.
  • The work is recognisable by tripods, measuring trolleys and markings; observe only from outside the track area.

Frequently asked questions

What does a construction firm with its own railway licence do?

It can run on the rail network with its own vehicles instead of buying every journey from another railway. For construction firms this is a big advantage: machinery and materials can be tied closely to the construction schedule. The price for this is its own safety management, its own staff and approved vehicles.

What is track surveying?

Determining the actual position of a track in space and comparing it with the planned position. From this comes the instruction for how far a track needs to be shifted sideways and in height. Without these target values, no machine can correct a track – it would only carry forward the existing state.

Which measurements are taken on the track?

Mainly five: the gauge between the rails, the cant as the height difference between the two rails on a curve, the alignment as the sideways deviation, the longitudinal level as the vertical course, and the twist as the change in cant over a stretch.

What are fixed points?

Permanently marked reference points beside the track, often set on masts or dedicated markers. They record the planned track position on the ground. Only through them can a target geometry be reproduced over years – even when the track itself has been shifted in the meantime.

Why does cant matter so much?

Because it counteracts centrifugal force on a curve. If it's too low, the force acts more strongly on the outer rail; if it's too high, a slow train loads the inner rail. That's why the permitted speed on a curve is directly linked to cant – and why it's measured carefully.

How do I recognise surveying work on the track?

By tripods with measuring instruments beside the track, people with levelling staffs or reflectors, coloured markings on sleepers and rails, and measuring vehicles that move noticeably slowly. This often happens long before the actual construction machine arrives.

Is it measured again after construction?

Yes. After lining and tamping, the achieved state is documented – as verification and as the starting value for the next maintenance cycle. This chain of measurements builds up the history of a track section over years.

May I photograph surveying work?

From publicly accessible locations, generally yes. The work area itself is off-limits: it lies within the track, movements can happen at any time, and barriers are binding. Don't speak to staff during the work – they have safety duties where distraction is dangerous.

Log a sighting of Schwalbe Baugesellschaft mbH & Co. KG

Vehicle, location and date logged in seconds – and visible to the community.

Download Traintrack on the App Store4.8(23 ratings)Get Traintrack on Google Play4.4(35 ratings)

Vehicles in the rolling stock database

More operators

Who is behind it

Groups, brands, manufacturers and operators – who owns whom and how to recognise them out in the field.

All railway companies →

Related guides from the blog

TT

Traintrack editorial team

The railway operator database is built from operational observation, community sightings and publicly available sources. Service contracts, fleets and owners change all the time – confirmed details are in the fact file, and anything subject to change is marked as such.

← All German railway operators